The Santa Clara City Council was told nearly $2 million was needed to repair the International Swim Center. While the public would narrowly support a bond measure that could help fund repairs, the ISC is not high on people’s list of priorities. Plus, after agreeing to waive City fees for nonprofit and youth sports, the Council walks back its decision and makes no decision. And, the timeline to bring BART to Santa Clara is pushed back again.
In order for Santa Clara to reopen the George Haines International Swim Center (ISC), it will need to spend $1.9 million. Those costs are one-time expenses, mostly for lead abatement, the fixing of gates to allow foot traffic to flow and replastering.
During a monthly update about the ISC, Cynthia Bojorquez, assistant city manager, told the Council that the City has already begun work on the canopy gutters and already fixed its broken boiler. Many more repairs are necessary before the pool can reopen. The news wasn’t promising for those hoping the ISC will be up and running soon.
Still, Borjorquez said provided the Council is willing to invest the money, City employees are doing all they can to get the pool operational in a timely manner. If the City is able to fund all the center’s needs — from the aforementioned gate replacement, replastering and lead abatement to showers, providing porta-potties and a slew of other minor problems — it would be able to reopen with a 200-person capacity as soon as the work is complete.
A study session prior to the agenda item detailed the public’s willingness to support a bond measure for infrastructure, including building a new swim center. The topic has been a frequent one at Council meetings lately. With more than $600 million in unfunded infrastructure needs, it is no wonder why.
However, just as with the community survey presented at the Council priority setting session earlier this month, the results of a voter survey show that the ISC is not a high priority for most voters.
The survey, conducted by Tulchin Research, asked 400 voters how likely they would be to support two different infrastructure bonds, one for $298 million and another for $598 million.
Both proposed measures saw roughly equal support and, according to the survey, would barely meet the supermajority threshold to pass such a bond.
Still, those results make several assumptions. The first is that those who said they were “leaning toward yes” supported the proposed measures. Another assumption is that the City would engage in “positive messaging” to “educate” the public — doublespeak for “influence.” Finally, getting to the needed 2/3 majority requires ignoring the survey’s margin of error, which is +/- 4.8%.
Most everything voters surveyed said they would support included road-related maintenance, e.g., fixing potholes, street repairs, making the roads safer. Replacing the ISC was in the lowest tier of support initially and only improved slightly when those surveyed were given “positive messaging” to “educate” them.
Cost for BART Station Swells, Timeline Pushed Back Again
The Council also held a study session updating them on Santa Clara’s forthcoming Bay Area Rapid Transit (BART) station. The above-ground station is part of a larger six-mile extension funded, in part, by a ballot measure in 2000. The station, one of four along the stretch, is set to be located near Santa Clara’s Caltrain station.
Since its inception, the project’s timeline and cost have shifted considerably. In 2019, the Valley Transit Authority (VTA) estimated that passenger service would begin in 2026. Since then, the cost has also ballooned, increasing from $5.5 billion in 2019 to $9.3 billion just a couple years ago to $12.23 billion.
Tom Maguire, with Santa Clara VTA, told the Council that the station underwent significant redesign, both for aesthetics and accessibility. That redesign is more than 60% complete, he said.
Further, he added, the Federal Transit Administration — the government agency from which VTA is seeking grant money to cover nearly half the cost of the project, has assured VTA that the cost is appropriate.
“The inflation of labor, materials and construction contractors have affected every part of the construction industry, and transit is no different,” Maguire said. “Yes, while $12 billion is a lot to pay for a six-mile station, [the Federal Transit Administration is] confident that our costs are in the ballpark. They are consistent with the costs that other transit agencies are paying elsewhere in the county.”
John Haggerty, a frequent Council commenter, said he only cares about “dollars and dates.” Given the cost and delays in construction, he said it is time to consider whether the station is worth the trouble.
“We could have built 12 stadiums, 12 major stadiums, with $12 billion,” he said. “The Empire State Building went up in 13 months, with 1930s technology, and this is going on forever.”
VTA now expects to complete the project in 2036.
Youth Sports Still Waiting to Hear on Exemption
After a reconsideration, a substitute motion, a second motion and a final motion, the Council adopted the new municipal fee schedule. In a narrow 4-3 vote, the Council exempted youth sports from paying any fees. But, after Vice Mayor Anthony Becker, who initially voted “yes,” misunderstood a portion of the motion, the Council reconsidered and defeated the exemption.
But that wasn’t the end of things. Two motions later, the Council nearly came back to the recommendation from the City manager’s office.
During a previous study session on the topic, the Council weighed the public benefit of waiving the fees and its need to bolster the City’s general fund in the wake of the pandemic.
The topic proved contentious. Mayor Lisa Gillmor iterated her desire to return to the days when the City did not charge fees for youth sports and nonprofits. However, some of her Council colleagues disagreed with the idea of giving such groups a free ride. Council Members Suds Jain and Karen Hardy contended that “free stuff leads to abuse.”
Jain said the City is in the situation it is in with the degradation of the ISC precisely because nobody ever set aside money for its maintenance. He doesn’t want to see the parks suffer a similar fate, he said.
Gillmor and Watanabe balked at the notion that such groups could ever be accused of abuse, with Watanabe calling it an “insult.”
Kenn Lee, the City’s finance director, told the Council the new fee schedule will collect $37.3 million, most of which will go to the general fund. Most departments have increased their cost recovery. An exception is the parks and recreation department, which is heavily subsidized, only recovering 14% of its costs.
While that number is higher than it used to be, Lee said it is still lower than the 23% average in neighboring cities.
“We shouldn’t be concerned about cost recovery. That is just a service we provide, for our community, for our kids, for seniors and others,” Gillmor said. “We want to encourage them to live nice, healthy lifestyles in our community. It is not about making money for us.”
City employees told the Council that the City collects $115,000 in field use fees a year, but the initial exemption was for all nonprofit and youth sports fees. Although City employees were not able to quantify how much subsidizing the groups would cost the City, the motion still passed, with Jain, Hardy and Park voting “no.”
After Becker’s consideration, a substitute motion amended the exemption to include only the youth sports and nonprofit fees detailed during the presentation, i.e., those that amounted to $115,000.
The Council defeated that motion, with Becker joining Jain, Hardy and Park in dissenting.
Jain then moved to adopt the fee schedule as recommended and directed City employees to return with details about exempting youth and nonprofits from fees.
The Council defeated that motion.
Gillmor took umbrage with the reconsideration, saying it looked “really bad” that the Council let several groups that spoke during public comments leave thinking they got an exemption. She said she was “disgusted.”
Finally, Watanabe proposed another motion, nearly identical to Jain’s with minor changes.
The Council passed that motion in a 6-1 vote, with Gillmor voting against it. After the vote, she congratulated the City employees sardonically.
The new municipal fee schedule goes into effect July 1.
Consent Calendar Spending
- A $507,546 amendment to a contract with David L. Gates & Associates, Inc. for the rehabilitation of Henry Schmidt Park.
- A $138.880 amendment to a contract with Life Scan Wellness Center for occupational medical services for the fire department.
- A six-month $280,000 extension to a contract with InfoSend, Inc. for utility bill print and mail services.
- A $35.696 extension to a contract with Accela, Inc. for subscription and support of the Citizen Request Management software. Total contract amount: $254,410.
- A $50,000 contract with Daniel Keen, a consultant, through 2025 to evaluate the performance of the city attorney and city manager. The contract has two one-year options at the mayor’s discretion.
The next regularly scheduled meeting is Tuesday, May 7 in the Council Chambers at City Hall, 1500 Warburton Ave. in Santa Clara.
Members of the public can participate in the City Council meetings on Zoom at https://santaclaraca.zoom.us/j/99706759306; Meeting ID: 997-0675-9306 or call 1 (669) 900-6833, via the City’s eComment (available during the meeting) or by email to PublicComment@santaclaraca.gov.